Planned Value (PV) =$23,000
Earned Value(EV) = $20,000
Actual Cost (AC) = $25,000
Budget At Completion = $120,000
Cost Variance (CV) = EV – AC = -5,000
Schedule Variance (SV) = EV – PV = -3,000
How is the Project doing?
Cost Variance = $20,000 - $25,000 = - $5,000 - Un Favourable
This means the project is not doing well, as the cost of work is more than planned.
Schedule Variance = $20,000 - $23,000 = -$3,000 – Un Favorable The Earned value was
$20,000 and the Planned value is $23,000. That means due to inflation or some other unforeseen factors,it took longer than planned to do the work.
Is the Project ahead or behind the schedule?
Schedule Performance Index (SPI) = EV/PV
0.869 ( < 1) 86.9%
Clearly the project is behind schedule by calculating the SPI < 1
Is the Project Under Budget?
Cost Performance Index (CPI) = EV/AC
0.8( < 1) <100%
Clearly the project is over budgeted as shown by calculating the CPI < 1
Estimated Cost and Time Calculations
Estimated Cost to complete this project based on given data.
Estimated at Completion = 120,000 / 0.8 = $150,000.00
Estimated Time to complete this project based on given data.
Estimated at Completion = 12 / .869 = 13.81 months (Just over 13 months)
Earn Value Chart